ST. JOSEPH – Berrien County Commissioners have decided what to do with more of the nearly $30 million the county has gotten in American Rescue Plan Act funds. With $6 million set aside for broadband projects, commissioners have agreed to spend another $15.8 million on county facilities maintenance work.
Commissioners have been debating how to spend the $30 million for more than a year. Early on, they decided to set aside $6 million to go toward the expansion of broadband service in the county. The county has spent $1.26 million of that amount and pledged the rest to match possible state grants that could be announced as soon as early June.
With the facility building projects, the county board hired a Berrien Springs firm, Bacchiocchi Construction, earlier this year to help them prioritize which projects to do. That prioritization was needed after county officials realized that it would cost more than originally expected do all the needed work.
The contract with Bacchiocchi includes $32,400 for the initial review of current and future projects including updated cost estimates as well as $557,384 for developing bid documents and scheduling orders. A separate charge for construction management will be approved at a future date.
County Administrator Brian Dissette noted earlier this month that project costs are expected to be higher than initially anticipated due to market volatility. He said there are no plans at present to augment the $15.8 million set aside in ARPA funds with contributions from the general fund, but that could happen if prices go up even higher.
Over $2.1 million of the $15.8 million has already been spent including the roof work approved by the county board earlier this month. Commissioners approved the low bid of $853,650 from Dudeck Roofing & Sheet Metal to replace the roofs at the Berrien County Jail and the South County Courthouse.
Projects to be funded with what remains of the $15.8 million include ones identified as involving life and safety issues, code violations, deferred maintenance, operational change and improved experience. Only those projects listed as the highest priorities will be done.
Several county facilities will see work done. They include the county facility at 2100 Empire in Benton Harbor, the health department on Napier Avenue, the courthouse in St. Joseph, the administration center in St. Joseph, the south county courthouse and three county parks.
Dissette noted that additional projects could be done and will be included in bid documents in the chance that they could be done if economies of scale are found if projects are bundled together.
Projects on the schedule to be done include the installation of a bullet resistant system in the County Administration Building, sidewalk and parking replacement work at the Berrien County Courthouse in St. Joseph and a variety of deferred maintenance work at the courthouse, the health department and the south county building.
The nearly $30 million in ARPA funds the county is getting also includes about $3 million for the south county 911 communications tower project being planned.
The county is still working to finalize the site for that tower after Native American artifacts and remains were found at the initial site near the former AEP operations center in Buchanan. Other sites being explored include one near the Buchanan Township fire department on North Main Street and Lake Michigan College land in Bertrand Crossing.
Commissioners also gave the go-ahead last week to buy land in Baroda next to the Road Department garage there. The owners of two adjacent properties have agreed to sell a total of 2.676 acres, for $58,000. A $2,000 option to purchase payment is being made to each owner. The final purchase is expected to be completed within the next year.