CITY OF NEW BUFFALO – ORDINANCE NO. 283

CITY OF NEW BUFFALO
BERRIEN COUNTY, MICHIGAN
ORDINANCE NO. 283

At a regular meeting of the City Council for the City of New Buffalo held at City Hall on November 16, 2026 and commencing at 6:30 p.m., the following Ordinance was offered for adoption by Council Member Robertson and was seconded by Council Member Knoll:

AN ORDINANCE TO AMEND ARTICLE 8 OF THE CITY OF NEW BUFFALO ZONING ORDINANCE, TO ADD A NEW SECTION Z8-14, ENTITLED “PERFORMANCE GUARANTEES”

THE CITY OF NEW BUFFALO (“City”) ORDAINS:

Section 1. Addition of Section Z8-14 to Article 8 of the City of New Buffalo Zoning Ordinance. That Article 8 is amended to add a new Section Z8-14, to read in its entirety as follows:

Section Z8-14 Performance Guarantees.

A. To ensure compliance with conditions imposed in accordance with this Zoning Ordinance, the City Council, Planning Commission, Zoning Administrator, or the Board of Appeals may require a performance guarantee of sufficient sum to assure the installation of those features or components of the approved activity or construction considered necessary to protect the health, safety, and welfare of the public and of users or inhabitants of the proposed development.
B. The features or components, hereafter referred to as “improvements,” may include, but shall not be limited to, survey monuments and irons, streets, curbing, landscaping, fencing, walls, screening, lighting, drainage facilities, sidewalks, paving, driveways, utilities, and similar items authorized by law.
C. Performance guarantees shall be processed in the following manner:
1. When required by the City, prior to the issuance of a building permit, the applicant or their agent shall submit an itemized estimate of the cost of the required improvements that are subject to the performance guarantee, which shall then be reviewed by the Zoning Administrator. The amount of the performance guarantee shall be 100 percent of the cost of purchasing of materials and installation of the required improvements, plus the cost of necessary engineering and inspection costs and a reasonable amount for contingencies.
2. The required performance guarantee shall be payable to the City and may be in the form of a cash deposit, certified check, irrevocable bank letter of credit, or surety bond acceptable to the City in its reasonable discretion.
3. Upon receipt of the required performance guarantee, the Zoning Administrator or their designee shall issue a building permit for the subject development or activity, provided it is in compliance with all other applicable provisions of this Zoning Ordinance and other applicable ordinances and codes of the City.
4. The Zoning Administrator, upon the written request of the obligor, shall rebate portions of the performance guarantee upon determination that the improvements for which the rebate has been requested have been satisfactorily completed as approved by the City. The portion of the performance guarantee to be rebated shall be in the same amount as stated in the itemized cost estimate for the applicable improvements.
5. When all of the required improvements have been completed, the obligor shall send written notice to the Zoning Administrator of completion of the improvements. Thereupon, the Zoning Administrator or their designee shall inspect all of the improvements and approve, partially approve, or reject the improvements with a written statement of the reasons for any rejections.
6. If partial approval is granted, the cost of the improvement rejected shall be set forth. Where partial approval is granted, the obligor shall be released from liability pursuant to relevant portions of the performance guarantee, except for that portion sufficient to secure completion of the improvements not yet approved.
7. The Zoning Administrator shall maintain a record of required performance guarantees.
8. In lieu of providing performance guarantees, the City and the applicant for a development proposal may agree to enter into a development agreement that would be recorded with the register of deeds or make other suitable arrangements as mutually agreed to by the City and applicant.
Section 2. Repealer. All ordinances or parts of ordinances in conflict with this Ordinance are repealed to the extent of any such conflict.

Section 3. Conflict.

A. Nothing in this Ordinance will be construed in such a manner so as to conflict with existing City ordinances except as otherwise explicitly stated herein.

B.Nothing in this Ordinance will be construed in such a manner so as to conflict with any State law.

Section 4. Savings Clause. The provisions of this Ordinance are severable. Should any word, phrase, sentence, or clause of this Ordinance be declared by a court of competent jurisdiction to be invalid or unenforceable, the same shall not affect the validity or enforceability of any other provision or part.

Section 5. Effective Date. This Ordinance is effective 20 days after its enactment unless otherwise provided by law.

The vote to approve and enact this Ordinance was as follows:

YEAS: Campbell, Knoll, Lijewski, Robertson, Price

NAYS: None

ABSENT/ABSTAIN: None

ORDINANCE DECLARED ADOPTED.

 

_________________________
Vance Price, Mayor

 

 

CERTIFICATION

I, Amy Fidler, the Clerk of the City of New Buffalo, hereby attest that the foregoing is a true and accurate copy of an ordinance adopted by the City Council for the City of New Buffalo, Berrien County, at a meeting of the City Council called and held on November 16, 2026, in accordance with the required statutory procedures.

 

_____________________________
Amy Fidler, Clerk