GANUM ADDRESSED MULTIPLE FACILITY ISSUES IN FIRST MONTH

New Berrien County Administrator Ganum is already tackling one of the county’s most pressing facility issues, namely, deciding where a new 9-1-1/Emergency Operations Center should be located.
By DEBRA HAIGHT
BCR Correspondent
         ST. JOSEPH, MI – He’s been on the job for less than a month, but new Berrien County Administrator Juan Ganum is already tackling one of the county’s most pressing facility issues. Namely, the county is still trying to decide where a new 9-1-1/Emergency Operations Center should be located.
         It was back in May when County Commissioners officially abandoned the idea of locating new center in the former Clark/AEP headquarters at 500 Circle Drive in Buchanan. The county had purchased the building in 2022 but sold it back to AEP in May after the costs of renovating the building turned out to be too high.
The resolution approved by the county board in May indicated that assessments conducted on the building showed that a capital investment of as much as $17.3 million would be needed to renovate and adapt the facility for the county’s purposes. That number did not include the cost of 911 communications infrastructure and equipment.
Last week, Ganum and County Board Chairman McKinley “Mac” Elliott both spoke about the issue of finding a new location for the 9-1-1/Emergency Operations Center. Ganum also mentioned the status of the $3 million FEMA grant the county had received to pay for part of the 500 Circle renovations.
Ganum said he attended a presentation last week by the Wold architectural firm on where the county goes from here in finding a new location. Wold was hired by the county a few years ago to oversee the 500 Circle project and is continuing to work with the county.
Ganum said that the county would have had 35,000 square feet of space available in the 500 Circle complex and county officials are now looking at how much space is actually needed and what is “absolutely essential.” He said that the number was whittled down to 26,000 square feet–a number he described as “still a very sizable facility.”
Ganum said the cost of constructing such a facility including the installation of technology, communications, and furnishings on county-owned land on Napier Avenue in Benton Harbor is “roughly approaching” $30 million.
“The other part of the discussion involved the existing FEMA grant that was approved for about $3 M,” he said. “We have to find out whether we can retain that grant and put it towards a new project with a new scope.”
He then talked about the other issue besides costs and location which is financing. “We’ve heard from [Community Development Director] Dan Fette that the outlook isn’t positive in regards to bonding,” he said. “The rates are going to increase, thereby adding potential significant costs to a project that’s financed by bonds.”
Elliott then offered his opinion on a possible alternative. He suggested that the county consider building onto the Empire Road site in Benton Harbor, which currently houses motor pool, printing, and genealogy/records. He estimated that building an addition there and buying all needed equipment and furnishings might cost $20 million.
“I think we may want to look at upgrading and remodeling that building,” he said. “That’s a fairly secure building already. Can we expand it and make it work? Then we’re looking at costs that are significantly less.”
Elliott also questioned whether they could justify building a 26,000 square feet facility on Napier. He also noted that the county would still need a satellite office in the south county for the sake of “geo diversity” and having back up services in another location.
“We don’t need nearly as much space,” he said. “I can tell you right now that my goal would be to do the whole thing including equipment, furnishings, and whatever else we need for $20 million.”
Elliott asked that the board’s executive committee meet this week to discuss options. “I think we need to re-examine this at the board level before we turn the [core planning] group loose to implement something,” he said. “We have to come up with a plan, and I’d certainly welcome input from the sheriff as well.”
In another facilities matter, County Commissioner Jim Curran reported on an ongoing mold issue at the South County Courthouse. He said that Buildings and Grounds Supervisor Don Trail told the Administration Committee that the situation was worse than originally thought.
The mold was found in the original part of the south county courthouse and not the addition built in 2004, specifically in the space occupied by the prosecutor’s office and the sheriff’s department.
Curran said that county staff have attached dehumidifiers to the HVAC system, a solution expected to prevent new mold from growing but not remediate the mold already in there.
Trail told the committee that they’ve already spent as much as $250,000 to address the problem including cleaning carpets and walls and replacing ceiling tiles. Now carpet and furnishings need to be replaced at an estimated cost of $175,000.
Curran said that Ganum is considering both adjusting the budget for the year to accommodate and filing an insurance claim.